The first of 2,500 tons of structural steel started going up early this week at the construction site of the new Our Lady of the Lake Children’s Hospital.

Construction crews also continue to pour concrete at the new facility. To date, more than 65,000 of the anticipated 95,000 square feet of first level concrete have been poured since early May. All first floor slabs are expected to be poured in the next month. The new facility is expected to open in the summer of 2019.

WAFB visited our construction site early one morning this week. Here are the clips from their visit:


 


 


 


To follow construction updates, including footage from a live web cam, and learn how you can support the new freestanding children’s hospital, visit letsbuildamazing.com.